Systems
Approach Needed | It's
much worse than that! | Apopka
Site Clarcona
Site | Reedy
Creek Site | Costs
vs. Benefits
Orange County, Florida's emergency response
system is based at Apopka, an Orlando suburb.
Dispatchers at the facility take citizens' 911 calls,
then contact appropriate agencies by way of a 28-
channel radio network. The 280-ft (85-m) antenna tower,
one of 11 in the system, is a frequent target for the
area's many lightning storms. High-resistance grounding
enabled a lightning strike to destroy expensive
transmitter equipment here. Similar incidents have cost
taxpayers more than $2 million over 10 years, but damage
ceased when the county installed a low-resistance,
all-copper grounding system.
Meteorologists call Central Florida "Lightning
Alley," and for good reason, because severe
thunderstorms occur there on an average of 130 days each
year, more than anywhere else in the country. Orange
County sits in the heart of the alley, and it sees more
than its fair share of damaged buildings, disrupted
power lines, fires and, unfortunately, injuries.
The county defends its 820,000 residents — 150,000 of
whom are seniors — with an extensive emergency response
system. When a citizen calls 911, dispatchers notify
response teams by way of a 28-channel radio network that
includes eleven transmitter sites, all equipped with
tall antennas to cover the county's more than 900 square
miles. But what happens when lightning disables the
communications system?
Tom Sorley knows. Sorley is supervisor of Radio
Services of Orange County's Public Safety Communications
Division, located in Orlando. It's his job to keep the
communications lines open, and the job hasn't been easy.
"We're in the most lightning-prone area of the country,"
he says, adding, "our antennas are up on 280-ft (85m)
lightning rods!
"One or two strikes per month on a large tower like
the one at our Apopka base site are routine between May
and October. They don't all do damage, but we have lost
our entire network at times, and every public service
agency is in jeopardy when that happens. We operate more
than 15,000 active IDs (each radio-equipped emergency
vehicle constitutes one ID, for example). Imagine what
would happen if we absolutely had to dispatch a police
cruiser and couldn't reach it!
"Lightning has also cost us a lot of money. The
Apopka site took a $13,000 hit to some transmitters the
other day, and we lost another $25,000 at Clarcona
earlier this summer. System-wide, we've been running
between $100,000 and $200,000 per year in lost equipment
due to lightning strikes. That's almost two million
dollars over the past 10 years!"
Systems Approach
Needed
Lightning protection is essentially the process of
directing strikes to ground and away from where they can
cause damage or injury. Doing that right requires a
properly designed, low-resistance grounding system. But
since many buildings — especially emergency service
facilities — have grounding systems that meet electrical
codes, why did Orange County have a problem?
Sorley explains: "Our facilities complied with the
codes that were in effect when they were built.
Lightning protection has come a long way since then, but
codes and protection systems take awhile to catch up.
Also, our system was designed and built by a number of
different contractors over the years. No single
individual or contractor understood, nor was responsible
for, grounding as a total system. Grounding and its
maintenance were just something everyone took for
granted. What we really needed, and what we now have, is
a total systems approach to lightning protection."
It's much worse than
that!
Orange County is active in a domestic terrorism task
force in Florida, created by Governor Bush. While
chairing its communications committee, Sorley was led to
John West, founder of Power & Systems Innovations (PSI), a 12-year-old Orlando-based company specializing
in power quality, grounding and lightning protection.
West understood what Sorley was up against, having upgraded
the 911 headquarters grounding system in nearby
Winter Park.
"I invited John to inspect a few of our sites,"
Sorley recalls, "after which I asked him if he thought
our systems were in bad shape. 'Oh no,' he answered.
'It's much worse than that!' That got my attention, so
we developed an action plan and got to work."
Sorley engaged Donnelly Engineering, based in
Orlando, design the new grounding systems. West served
as a technical consultant. Sorley split the project into
two parts. "In Phase I," he recalls, "the issue was to
protect lives by making certain that another lightning
strike wouldn't take us off the air. In Phase II, we'll
go back and add improvements like better surge
protection and tie-ins to other systems that aren't
directly part of the 911 emergency response network."
THREE SITES PROVIDE EXAMPLES
Improvements at three of the county's transmitter
sites illustrate work accomplished system-wide under
Phase I. The sites are in Apopka, Clarcona and Reedy
Creek in the Orlando suburbs.
Apopka Site
The Apopka site houses the 911 communications hub,
along with county offices, courtrooms and dispatchers. A
280 foot (85 m) antenna tower, complete with grounding
and lightning protection systems, was installed 10 years
ago. Located immediately adjacent to the building, the
tower is surrounded by paved area on the remaining three
sides.
West found that the grounding "electrode" serving the
tower and transmitter room was actually a length of
ordinary steel all-thread rod driven into the ground
near the tower base. Resistance to earth was an
astonishing 550 ohms (Figure 1), 22 times the
maximum resistance cited by the National Electrical
Code® and more than two orders of magnitude higher than
the level recommended by such standardssetting
organizations as IEEE and TIA/EIA. The makeshift
electrode was supplemented by a length of buried cable
(counterpoise) which, in turn, was connected to one of
four copper strips leading to copper firewalls. West
discovered that the contractor had simply buried three
of the copper strips in the ground, never connecting
them to the electrodes.
 |
Figure 1. The Apopka
antenna tower was originally grounded to a length
of steel all-thread rod and a counterpoise (a
length of buried bare AWG 4/0 copper cable).
Ground resistance was 550 ohms, far too high to
provide useful grounding and excessive even for
lightning protection. Lightning surges had often
bypassed the electrode, destroying equipment
inside the transmitter
building. |
Donnelly and West installed a new 60-ft (18-m)
copperclad electrode close to the tower (Figure
2) on the premise that a lightning strike would tend
to travel vertically. A deep electrode was used because
of the soil's high resistivity. The new electrode's
resistance is an acceptable 4.3 ohms.
 |
Figure 2. Bare AWG 4/0
copper conductors are exothermically bonded to a
new 60-ft (18-m) grounding electrode at the Apopka
tower base (lower left) replacing the all-thread
rod. Resistance to earth is 4.3
ohms. |
Donnelly and West next ran AWG 4/0 leads from the new
electrode to a copper bus on the tower (Figure
3a), which was then connected to a second bus
(Figure 3b) which served as a junction point for
the coaxial cable shields, and to the firewalls and
copper strips shown in Figure 4. The copper
strips were left in place but were supplemented with
additional lengths of AWG 4/0, and all four strips were
bonded to the counterpoise.
Figure 3. Weatherproofed leads from antenna
cable shields (Figure 3a) are bonded to the large
bar (Figure 3b); and a lead from there
connects to a second copper bar (Figure 3a,
lower right), which was added for ease of access.
An exothermic bond connects the bar to the
grounding electrode. |
New, AWG 2/0 grounding conductors
were piggybacked over existing AWG 2 conductors at the
tower's three sets of guy wires (Figure 5). The
heavier conductors were run to three new 60-ft (18-m)
grounding electrodes. Chemical-type electrodes had been
installed 10 years earlier, but because they had never
been serviced, resistances had risen to between 35 and
64 ohms.1
Figure 4. Only one of the four copper
strips shown leading from the site's two antenna
cable firewalls was actually connected to the
counterpoise. The other three were simply buried.
The copper strips are now augmented with AWG 4/0
copper securely bonded to the firewalls and to the
new grounding electrode. |
Figure 5. One of three sets of five guy
wires, each supporting the Apopka tower. New AWG
2/0 ground leads from the wires connect to a new
lowresistance electrode. Resistance at the new
electrodes ranges from 5.3 to 6.7 ohms.
|
Resistance of the new deep electrodes ranges between
5.3 and 6.7 ohms. A clear indication of their
effectiveness can be seen in the 150-160 mA of RF
current they draw off the guy wires.
Leaking Roof + Poor Grounding = Lost
Equipment
The equipment room houses more than $2 million worth
of transmitters, switches and auxiliary equipment
(Figure 6). West found the two rows of equipment
racks bonded to the firewalls by way of a halo ground,
and from there, to the main grounding electrode and
counterpoise outdoors (Figure 7a and 7b).
Figure 6. Orange
County technician Dave Hazen checks transmitter
equipment at the Apopka site. The room, one of
eight like it in the county system, contains more
than $2 million worth of communications gear.
Equipment racks were originally grounded by way of
a halo ground circling the walls, but equipment
chassis themselves were never bonded to the
racks. |
Figure 7. Schematic diagram of the Apopka
site grounding system: as originally installed
(Figure 7a), and as upgraded (Figure
7b). Green lines identify grounding
conductors; copper color indicates new grounding
plates. Improvements include bonding to equipment
cabinets and racks, an additional halo ground,
copper grounding plates, a lowresistance grounding
electrode and exothermically welded
bonds. |
The equipment chassis (cabinets) themselves hadn't
been bonded to the racks. During a thunderstorm in mid-
2002, a leak in the building's roof left a trail of
water down one of the racks and onto the concrete floor.
A lightning strike followed the moisture trail (wet
concrete is a pretty good conductor), destroying
expensive transmitters and leaving the 911 system short
by two communications channels (Figure 8a and
8b).
 |
Figure 8a. Water stains
on an equipment cabinet left by a leaking roof.
The moisture trail, which continued to the
concrete floor, allowed a lightning strike to
destroy expensive transmitters and took two
communications channels off the air. |
 |
Figure 8b. Dave Hazen
holds circuit boards destroyed by the lightning
strike. The damaged equipment put public safety at
risk and cost $13,000 to replace. Lightning caused
almost $2 million in similar damage to the entire
system over 11 years. An all-copper grounding
system installed in 2002 put an end to the damage,
improving public safety and eliminating high
repair costs. |
The new grounding system designed by Donnelly
includes several features intended to prevent that sort
of incident from recurring:
- First, all equipment chassis were firmly grounded
with AWG 2 copper. The heavy leads are bonded to a
series of copper ground plates mounted at the top of
the overhead rack supports. The plates are connected
to each other in a halo ring made from bare AWG 2/0.
Equipment racks are also bonded to the plates
(Figure 9a).
- A second AWG 2/0 halo was mounted on the comm room
walls and connected to the inner ring, again using
copper plates. Bolted connections on the plates ensure
sound bonding. More AWG 2/0 connects both halos to the
copper firewalls.
- Rubber mats were placed under equipment racks to
help preclude a conductive path (Figure
9b).
- Finally, an exothermically bonded connection was
made between the halos and a conductor leading
directly to the new grounding electrode system.
Figure 9a. A copper plate connects several
equipment chassis grounding conductors with an AWG
2/0 halo ground (upper left).
|
 |
Figure 9b. Insulated mats
installed under equipment racks at Apopka help
prevent lightning from seeking out a watersoaked
concrete floor, as it did after the site
experienced leaking roof. |
The communications system at the Apopka site is
powered by the building's electrical system; however,
the only grounding circuits between the two systems are
the green wires in branch circuits. This arrangement is
Code-compliant but not recommended, and Donnelly and
West will improve it in Phase II, when both grounding
systems will be interconnected. This change will create
a robust and reliable ground path for the entire Apopka
complex.
Clarcona Site
The Clarcona transmitter site (Figure 10) is
smaller than the Apopka hub, but Donnelly and West found
it to be plagued with similar problems. Like Apopka, the
site had taken severe lightning damage due to high
resistance electrodes, a lack of proper bonding
(Figure 11), and inappropriate grounding at
equipment cabinets.
 |
Figure 10. Like the
Apopka hub, Orange County's smaller Clarcona site
suffered from high ground resistance, inadequately
maintained chemical electrodes, poor bonding and
ungrounded equipment cabinets. Upgrades include a
new 60-ft (18-m) deep electrode with less than 5
ohms resistance, firm bonding of all connections,
installation of heavy copper grounding conductors
to all equipment cabinets plus new halo grounds in
the comm room. |
 |
Figure 11. Corrosion
raised resistanceat an existing cable shield
ground connection on the Clarcona
tower. |
The total value of equipment at the site is nearly $2
million, not counting $800,000 in equipment belonging to
the local community. The $25,000 loss the site suffered
in 2002 seems small but, as Sorley observes,
"Communications is a rapidly changing technology, and
some of the older equipment we lose has to be upgraded
with newer models. It’s not just the equipment that is
destroyed, but also every unit like it at all of our 11
sites has to be changed in order to maintain
compatibility. That multiplies the cost of a single
strike."
The grounding team's first order of business was to
replace high-resistance grounding electrodes at the
tower and guy wires with five 60-ft (18-m) copper-clad
rods. The new electrodes register only 3.4 ohms
resistance.
AWG 2/0 conductors were bonded to the tower and to
the station's two firewalls. An obviously corroded
grounding connection to the tower was replaced with a
1/4-in (6.3-mm) thick copper plate (Figure
12).
Figure 12. A copper bar, large conductors
and exothermic welds form secure bonds to the
Clarcona tower, replacing the flimsy connection
shown in Figure 11. |
Clearly marked grounding terminals on equipment
cabinets were never connected (Figure 13). As at
Apopka, the oversight left the cabinets grounded only
through cable shields and the green wires in their
respective power cords. The installation was not in
accordance with the manufacturers’ instructions, and not
adequate from the standpoint of lightning
protection.
Figure 13. A clearly marked but unused
grounding terminal, evidence that equipment
cabinets had not been properly grounded. Cabinet
racks were grounded, but chassis were grounded
only through cable shields and power cords. The
practice did not provide adequate lightning
protection. |
Donnelly and West bonded the cabinets and racks with
AWG 2 copper strung overhead to connect with copper
plates on a new AWG 2/0 halo ground on the walls. The
halo, which also functions as a grounding point for air
conditioners and other auxiliary equipment, is bonded to
the copper firewalls and to the main grounding electrode
system outside the building (Figure 14).
Figure 14. Copper plates in a halo ground
surrounding the Clarcona site communications room.
The plates are bonding points for ground leads
from equipment racks and cabinets and auxiliary
equipment such as air conditioning
units. |
Reedy Creek Site
One of the 911 system's three repeaters is located at
Reedy Creek (Figure 15). The site, several miles
from Orlando, is in moist terrain underlain by what
Floridians call "sugar sand", a fine-grained silica that
provides good drainage but has absolutely terrible
conductivity.
 |
Figure 15. Reedy Creek,
one of Orange County's two remote repeater sites,
is underlain by highresistivity "sugar sand." Poor
soil conditions, along with neglected
chemical-type electrodes, raised the site's ground
resistance to more than 1,000
ohms. |
Chemical-type electrodes had originally been
installed to enhance the soil conditions. (Salt in the
electrodes leaches into the ground, raising
conductivity.) As at Apopka, the electrodes had not been
maintained, and at the time West inspected them,
resistance was more than 1,000 ohms.
The site was also equipped with an AWG #2 tinned
copper ground ring at the base of the transmitter
building. The ring was in satisfactory condition, so
West and Donnelly tagged their new system to it
(Figure 16a).
New electrodes had to be driven 120-ft (37-m) deep to
gain satisfactory resistance levels — between 3.5 and
4.4- ohms in this case (Figure 16b). One
electrode was installed at the tower base and four
others outside the corners of the perimeter fence, about
15 ft (5 m) from the building. These were exothermically
bonded to a new AWG 2/0 bare copper ground ring
(Figure 17) at the fence and to lengths of AWG
2/0 extending to the pre-existing tinned-copper ring and
its chemical electrodes. The resulting "star" grounding
net directs lightning energy outward and into the ground
far from the transmitter's sensitive electronic
equipment.
 |
Figure 16a. Arrows
identify new (foreground) and old (rear) grounding
electrodes near the tower base (far right) at the
Reedy Creek repeater, as seen during installation.
Resistance of un-maintained chemical rods was
higher — more than 1,000 ohms. AWG 4/0 bare copper
grounding electrode conductors are bonded with
exothermic welds.
Figure 16b.
Resistance of the new rods ranges between 3.5 and
4.4 ohms, levels that are both low enough to
ground sensitive electronic equipment and suitable
for reliable lightning protection.
|
 Figure 17. Schematic diagram
of the Reedy Creek grounding system as originally
installed (blue lines) and as upgraded (green
lines). Upgrades include five new 120-ft (37-m)
deep, low-resistance electrodes, an AWG 4/0 ground
ring at the fence line, tie-ins to the existing
system and exothermic welds
throughout. |
Costs vs.
Benefits
The Phase I upgrade cost the county $150,000 in
materials, labor and consulting fees. Public officials
understandably think twice before spending that kind of
money burying wire. But Tom Sorley is convinced that the
county's investment will pay off. "We're talking about
saving lives here, so our ultimate goal is to eliminate
interruptions from lightning, period. We don't ever want
any downtime! Since completing Phase I, we've gone
through one-half of this year's storm season without
problems. It may be too early to tell yet, but I think
we have a winner.
"As for costs, you first have to look at what we're
protecting. The entire emergency response system cost
the taxpayers $30 million; the towers accounted for
about a third of that. The major cost is tied up in very
expensive equipment. Replacing and repairing that
equipment has cost us nearly $2 million."
"Another benefit that's come out of this is a
system-wide performance, inspection and maintenance
program. It will enable us to monitor how we're doing,
find areas that need special attention and provide
records for future reference. The program also spells
out specific preventive maintenance steps."
John West is confident that the new grounding system
will do its job. "Bob Donnelly and I live and work
here," he says. "And the public can see the result of
our work with every storm. We've been at this business
for a dozen years, and not one of our clients has ever
lost a single piece of equipment after we installed a
proper grounding system. We insist that our clients
adhere to our specs — and those specs always include
copper. That's the only way we'll take a job."
That's confidence. That's copper.
The Principals
John West is president of Power &
System Innovations, Inc. (PSI), Orlando, Florida.
Founded in 1992, PSI provides products, services and
consulting related to power quality, power protection,
surge protection, grounding, lightning protection and
other anomalies that can damage equipment and/or cause
data loss. PSI also designs, installs and services a
broad range of protection equipment and systems. Further
information about PSI can be found at the company's Web
site, http://www.psihq.com/,
or by calling them at (407) 380- 9200 or (800)
260-2259.
Robert L. Donnelly, P.E., is
president of Donnelly Engineering, an Orlandobased
electrical engineering and design firm specializing in
grounding and lightning protection issues. He can be
reached at (407) 351-3085, fax (407) 351-5149, email:
donnellyPE@aol.com.
Tom Sorley is supervisor, Radio
Services, of the Public Safety Communications Division,
Orange County, FL, a position he has held since 2000.
Mr. Sorley is responsible for all radio communications
equipment in the county, including links to the 911
emergency response system. In 2002, Sorley initiated and
supervised Phase I of the major upgrade to electrical
grounding systems and lightning protection at the
system's 11 transmitters. Mr. Sorley can be reached at
(407) 836- 2792 and at tom.sorley@ocfl.net.
Footnotes
1. Chemical-type electrodes are
quite capable of providing low resistances and are
suitable for many applications with sensitive electronic
equipment. However, the electrodes must be serviced
according to manufacturers' specifications in order to
guarantee that low resistance levels are maintained over
time.
This publication has been prepared
solely as resource material for the use of individuals
involved in the specification, design, selection and
installation of electrical systems. It has been compiled
from information provided by one or more of the parties
mentioned herein and other information sources Copper
Development Association Inc. (CDA) and/or the relevant
parties believe to be competent. However, recognizing
that each system must be designed and installed to meet
the particular circumstances, CDA and the parties
mentioned in this publication assume no responsibility
or liability of any kind including direct or indirect
damages in connection with this publication or its use
by any person or organization, AND MAKE NO
REPRESENTATIONS OR WARRANTIES OF ANY KIND RELATED TO ITS
USE, ACCURACY, COMPLETENESS, UTILITY, AVAILABILITY OR
DOCUMENTATION. |